Luchtsingel Fase 5 completed!

28-11-2013

In the middle of the night, on November 3rd, two sections of the Luchtsingel were lifted in place above the railwail track. During this night train service was suspended for 5 hours. Enough time to built are bridge. Around 01.00 the contractor was ready to go, but because of a problem with the cutting off of the power supply, it wasn't until 3.30 that we could finally start. Once we got the green light, the first part of the bridge was lodged in place in less than 20 minutes. The second one took slightly longer, but we got the job done in time.